August 14, 2009

Work started/completed from July 11 to August 14

  • The piles being driven along University Avenue were completed.
  • Work on tiebacks for the pilings along University Avenue was started.
  • Underpinning work continues on Rand and Sibley halls.
  • The storm and sewer borings under Rand Hall were completed.
  • A temporary blacktop drive and parking area was completed at the Foundry.

 

Upcoming Activity

  • Tieback pull-tests will begin on the piles along University Avenue.