August 14, 2009
Work started/completed from July 11 to August 14
- The piles being driven along University Avenue were completed.
- Work on tiebacks for the pilings along University Avenue was started.
- Underpinning work continues on Rand and Sibley halls.
- The storm and sewer borings under Rand Hall were completed.
- A temporary blacktop drive and parking area was completed at the Foundry.
Upcoming Activity
- Tieback pull-tests will begin on the piles along University Avenue.